Discover the benefits of Danfoss APP high-pressure pumps and iSave ERDs
| Four months from design to a complete SWRO plant A new Jamaican luxury hotel set the bar high for its SWRO plant, looking for best-in-class OPEX, extensive control automations, and plug-and-play simplicity. But the project’s lead time was just four months from design to commissioning. Gefico and Danfoss cooperated to deliver the energy-efficient 1800 m3/day plant in record time. |
|
|
|
|
| |
|
|
|
|