Docket: 19-1461 Opinion Date: April 21, 2020 Judge: ROVNER Areas of Law: Business Law, Construction Law, Contracts |
Skyrise bid $950,000 to supply “stick building” rough frame carpentry for building housing units near the University of Wisconsin-Oshkosh. Upon receiving a letter of intent from Annex, the general contractor, to enter into a contract, Skyrise blocked the project on its calendar and declined other work. Skyrise delayed returning the actual proposed contract for two months. Amex rejected Skyrise’s subsequent proposals for a broader scope of work and a different payment plan and awarded the carpentry contract to another firm. Skyrise sued for breach of contract, promissory estoppel, negligent misrepresentation, violation of the Illinois Consumer Fraud and Deceptive Business Practices Act, and violation of the Wisconsin Deceptive Trade Practices Act. The Seventh Circuit affirmed summary judgment in favor of the defendants. Although the parties signed various proposals during their negotiations, no contract formed. The undisputed, objective evidence demonstrates that both parties intended for their relationship to be governed by a detailed contract that remained under review until Skyrise ultimately rejected that contract by making material alterations. Skyrise knew or should have known, that the negotiations could fall apart before the parties entered into a binding agreement. Annex never represented to Skyrise that it had the framing subcontract. |